Applying COCOMO II for a DO-178C Safety-Critical Software Effort Estimation

Lucas Pereira dos Santos, Maurício Ferreira

Journal of Aerospace Technology and Management · 2019

doi:10.5028/jatm.v11.1031 (opens in a new tab)

We email you when a new notice or a question about this paper appears.

Abstract

This paper provides a real example of applying COCOMO II as an estimation technique for the required software development effort in a safety-critical software application project following the DO-178C processes. The main goal and contribution of the case study is to support the research on software effort estimation and to provide software practitioners with useful data based on a real project. We applied the method as it is, by correlating the effort multiplier factors with the complexity and objectives introduced by the DO-178C level A application, resulting in an estimated effort. The rationales for each scale factor and effort multiplier selection were also described in detail. By comparing the estimated values with the actual required data, we found a magnitude of relative error (MRE) of 40% and provided alternatives for future work in order to increase the effort estimation accuracy in safety-critical software projects.

Abstract licence: CC BY

Reads

Read by people on this page

None yet.

Checked or read by AI through naulon

None yet.

A person counts once a day per paper. We keep no cookie and no address: a reader is a hash that changes every day. Any month under five reads shows no number.

Are you an author?

Is this your paper?

Claim it to add your note and be paid when agents cite it. Free.