Skip to content
naulon
Not checkedNot checked for notices yet.

Establishing engineering S-curves to evaluate supervision engineer allocations for highway construction projects

Shih-Hsu Wang, Wei-Chih Wang, Pei-Yuan Hsu and 2 more

Journal of Civil Engineering and Management · 2016

doi:10.3846/13923730.2014.928363 (opens in a new tab)

We email you when a new notice or a question about this paper appears.

Abstract

An engineering consultant firm needs to allocate engineers to supervise a highway construction project in each month during the construction phase. Properly assigning the supervision engineers under a cost-plus-fixed-fee contract has been a key factor affecting the profitability of the firm and the quality assurance of the project. Assigning too many engineers will be a waste, while allocating too few engineers may harm the supervision quality. This work proposes a two-stage model to develop engineering S-curves (called ES-curves) for planning and controlling the engineering super­vision schedule. In the planning stage, a predictive ES-curve model is established based on historical ES-curves. In the controlling stage, an ES-curve is built according to the relationships between the engineering progress and construction progress. A cluster analysis and regression analysis are applied to the model development. A case study demonstrates that the produced ES-curves can help management in planning and evaluating when to increase or decrease the number of supervision engineers assigned to a project.

Abstract licence: CC BY

References28

    28 more references, whose wording the paper’s licence keeps private.

    Reads

    Read by people on this page

    None yet.

    Checked or read by AI through naulon

    None yet.

    A person counts once a day per paper. We keep no cookie and no address: a reader is a hash that changes every day. Any month under five reads shows no number.

    Are you an author?

    Is this your paper?

    Claim it to add your note and be paid when agents cite it. Free.