Forecasting the Project Duration Average and Standard Deviation from Deterministic Schedule Information
Pablo Ballesteros-Pérez, Alberto Cerezo-Narváez, Manuel Otero-Mateo and 3 more
Applied Sciences · 2020
doi:10.3390/app10020654 (opens in a new tab)
We email you when a new notice or a question about this paper appears.
Abstract
Most construction managers use deterministic scheduling techniques to plan construction projects and estimate their duration. However, deterministic techniques are known to underestimate the project duration. Alternative methods, such as Stochastic Network Analysis, have rarely been adopted in practical contexts as they are commonly computer-intensive, require extensive historical information, have limited contextual/local validity and/or require skills most practitioners have not been trained for. In this paper, we propose some mathematical expressions to approximate the average and the standard deviation of a project duration from basic deterministic schedule information. The expressions’ performance is successfully tested in a 4100-network dataset with varied activity durations and activity durations variability. Calculations are quite straightforward and can be implemented manually. Furthermore, unlike the Project Evaluation and Review Technique (PERT), they allow drawing inferences about the probability of project duration in the presence of several critical and subcritical paths with minimal additional calculation.
Abstract licence: CC BY
Reads
Read by people on this page
None yet.
Checked or read by AI through naulon
None yet.
A person counts once a day per paper. We keep no cookie and no address: a reader is a hash that changes every day. Any month under five reads shows no number.
Are you an author?
Is this your paper?
Claim it to add your note and be paid when agents cite it. Free.