Failure of a Pendent Reheater Tube in a 110 MW Thermal Power Plant

Saha Atanu, Roy H., Shukla A.K.

High Temperature Materials and Processes · 2014

doi:10.1515/htmp-2013-0052 (opens in a new tab)

We email you when a new notice or a question about this paper appears.

Abstract

This investigation was conducted to examine the probable cause of failure of one pendent reheater tube of a 110 MW thermal power plant. Preliminary macroscopic examinations along with visual examination, dimensional measurement, chemical analysis, evaluation of mechanical properties, oxide scale thickness measurement were carried out to predict the probable cause/causes of failure. In addition, optical microscopy was a necessary supplement to understand the reason for the failure. It was concluded that due to progressive erosion caused by the high velocity flue gas streams on the fire side wall, the tube had thinned down and could not cope the prevailing working stress. As a result, the affected areas of the tube suffered plastic deformation. Apart from that, formation of micro creep cavities due to rise in tube metal temperature (on the steam side) at localized places led to initiation of minor cracks before culminating to final rupture. The final failure is due to both these mechanisms occurring simultaneously.

Abstract licence: CC BY

Reads

Read by people on this page

None yet.

Checked or read by AI through naulon

None yet.

A person counts once a day per paper. We keep no cookie and no address: a reader is a hash that changes every day. Any month under five reads shows no number.

Are you an author?

Is this your paper?

Claim it to add your note and be paid when agents cite it. Free.