S-curve modelling in early phases of construction projects
Nives Ostojić-Škomrlj, Mladen Radujković
Građevinar · 2012
doi:10.14256/jce.714.2012 (opens in a new tab)
We email you when a new notice or a question about this paper appears.
Abstract
The methodological procedure for forecasting cost distribution over time is given for the project realization phase using cost s-curves for three different types of structures: building, tunnel, and motorway. Three different approaches are used, and their results are correlated and presented in form of mathematical regression expressions and appropriate diagrams. The proposed methodology can be used for cash flow forecasting during all phases of construction projects, specially in the earliest phase in which detailed information about the project is scarce.
Abstract licence: CC BY
Reads
Read by people on this page
None yet.
Checked or read by AI through naulon
None yet.
A person counts once a day per paper. We keep no cookie and no address: a reader is a hash that changes every day. Any month under five reads shows no number.
Are you an author?
Is this your paper?
Claim it to add your note and be paid when agents cite it. Free.